How to construct a building in Russia to the Western European quality and within a predictable budget?
It seems easy – just collect historical data of similar projects and prepare the works’ budget, find a talented architect to develop the project’s concept, organize it’s verification/approval for compatibility with the local construction norms, order the design and tender documentation from reputable design consultants, ensure the coordination between all parts of the design, organize tenders for the construction works, control the quality of all prepared contracts, of the design documentation and of the building works;
✔ Organization and coordination of pre-project works (development of design and master plan concepts, various surveys and investigations, obtainment of the technical conditions for connection to the external networks ecc.);
✔ Organization and coordination of various design works (architectural, structural, indoor M&E systems, external networks). Preparation of technical specifications for design, surveys’ and investigations’ contracts;
✔ Quality control of the design documentation and coordination of its various parts;
✔ Submitting the design documentation to the State or Non-State Expertise, to Industrial Safety, Fire Safety and Ecological expertise;
✔ Management of approvals’ procedure with State authorities.
✔ Preparation of the construction budget, tender documentation, general construction programme, financing schedule;
✔ Organization of tenders;
✔ Preparation of construction contracts in their general and technical parts, organization of a legal review of prepared contracts;
✔ Coordination of the relations between the Customer, the General Contractor and the Architect (General Designer). Organization of project meetings between involved parties;
✔ Review and issuing of the “approval to construction” for working documentation / shop drawings;
✔ Supervision of ongoing construction works for compliance with design, norms, quality requirements and compliance with contractual specifications; moreover for observance of construction technologies and usage of proper materials;
✔ Setting of the Safety Control System at construction site;
✔ Organization of interim commissioning of the performed works as per local norms requirement;
✔ Control of the ongoing construction, material and equipment delivery terms to achieve the milestones of the Contractual Construction Programme;
✔ Participation in the site inspections by various State construction supervision departments;
✔ Organization of the handing over and commissioning process of the completed project to the Client and with the Authorities.
✔ Preparation of the construction budget, correction of the budget concurrently with the project’s implementation;
✔ Monitoring of the interim project cost and the cost-to-complete values and of their compliance with the budget. Correction in case of necessity of the Project Financing Schedule;
✔ Coordination of the project management activities and reconciliation of the financial records with Economic, Financial and Accounting departments;
✔ Management financial accounting for the subcontractors’ and the client’ contracts;
✔ Preparation of the final and interim Project’s Profit and Loss Statements; Preparation of the economic Registers of project Agreements;
✔ Preparation of the project reports for the Client or Investor.
✔ Study of the project’s contracts and technical documentation, of the correspondence, law and code limitations related to the performance of the Parties in relation to their contractual liabilities;
✔ Joint work with Client’s Legal Department or Advocate. Pretrial claim correspondence with Client’s counterparties;
✔ Selection of the project documents and preparation of the expression of requirements for Forensic Building-Technical Examination and for the further legal defense of the Client in court.
2019-2020 | A number of MEP design projects in luxury segment - private residences, Russia |
Recruiting staff to design department, KPI planning introduction, design offers calculation and contracts preparation, design projects management, design quality control for GT-AT LLC (Moscow). | |
2018 | Renovation of the «TRANSNEFT» oil company headquarters building , Evolution Tower, Moscow-City |
Delivery and installation of the architectural bronze decoration structures and the brass panels claddings within a fit-out project of the public zones of the building. Project Director for VenetoGroup LLC (Moscow). | |
2017 | Construction of "DYNAMO" football stadium and ice hockey arena, Moscow |
The design works management for CODEST International S.r.l. | |
2017 | Restoration and expansion of a historical building «Gardener house» at Denezhny lane, 5, Moscow |
Design and construction works' management. | |
2014-2016 | Construction of «Sports and fitness complex for Vankorneft JCS», Divnogorsk, Krasnoyarsk region |
Leading the design team of General Designer company. Organizing the site engineering surveys. Control of design documentation, contract and financial management, design approvals by the State and Non-State Expertise, correspondence to the Client and the Subcontractors, reporting to the company shareholders. | |
2014 | Construction of «Hyundai Flagship Store» at Novy Arbat, 21, Moscow |
Glass facade delivery within the building reconstruction project. | |
Contracts and Price breakdowns preparation, correspondence to the Client and Investor, financial claims, design control and coordination, preparation of performed works certificates, project consulting. | |
2014 | Design of «Bogoyavlensky Church shop bldg.», Khimki, Moscow Region |
Development of architectural concept drawings, leading the design team. | |
2013-2014 | Technical renovation of «Particle Board Plant «Kronospan», Elektrogorsk, Moscow Region |
Development of basic (stage “P”) and detailed (stage “R”) design documentation. Leading the design team. | |
2013 | Fit-out of «eastconsult» company Moscow office |
Development of interior layout and design concepts, MEP design concept, leading the design team, control of M&E external designers. Managing the fit-out works: contracts management and technical supervision to contractors, procurement and budget control. | |
2012-2013 | Design of «Wet Electrostatic Precipitator» at the «Particle Boards plant of «IKEA Industry»», Podberezie, Novgorod region |
Development of basic (stage “P”) and detailed (stage “R”) design documentation. Leading the design team. Obtainment of the State Expertise approval. | |
2012 | Construction of «Leninsky, 119 - business-center» building in Moscow |
Design of facades structural glazing. Leading the design and construction site supervision team. | |
2012 | Technical audit at property disposal of «PHLEIDERER» Particle Boards plant», Podberezie, Novgorod region |
Preparation of technical due diligence report for “IKEA Industry”. | |
Verification of the permitting documents, design and commissioning documentation of the completed construction, investigation of the actual state of buildings, plants and M&E systems. | |
2012 | Construction of «GoodZone» shopping mall, Moscow |
Preparation of expertise report on roofs construction for "Drees & Sommer". | |
2012 | Fit-out works at «Beauty shop «AVEDA» at «Lighthouse» business center, Valovaya str., 26, Moscow |
Managing design and fit-out works, commissioning of the completed works to the landlord. |
2011-2012 | Technical audit at property disposal of «Gagarin Plywood plant», Gagarin, Smolensk region |
Preparation of technical due diligence report for “IKEA Industry”. | |
Verification of the main permitting documents, design and commissioning documentation of the completed construction, investigation of the actual state of buildings, plants and M&E systems. Coordination of laboratory tests of the soil and the drainage water. | |
2011 | Technical audit at property disposal of «BluRay discs production plant» for «SONY DADC», Borovsk, Kaluga region |
Preparation of technical due diligence report for “SONY DADC”. Checking of main permitting documents, design and commissioning documentation of the completed construction, investigation of the actual state of buildings, plants and M&E systems. | |
Development of Fire Safety documentation. Fence and external lighting system design. | |
2011-2012 | Installation of technological plant at the Waste incineration plant#3 of «EVN-Ekotechprom», Moscow |
Design and installation of the Ashes tanks cable heating system. | |
Control of design and installation works, contracts preparation and commissioning coordination, development of special software to process technological plant data. | |
2011-2013 | Construction of «Laminate floors production plant «UNILIN flooring», Dzerzhinsk, Nizhny Novgorod region |
“Technical client” functions: Leading the site supervision and design teams. Contracts and tenders management. | |
Fit-out design for the office building, structural design of the concrete floors and of the machinery basements. | |
2011 | Reconstruction of sawmill plant «Binderholz», Kem region, Karelia |
Sale preparation, master plan consultations. | |
2011 | Bituminous roof tiles production plant «Tegola Canadese», Davydovo, Orekhovo-Zuevo region. |
New construction consulting. Coordinating Environmental Impact assessment (OVOS) preparation. | |
2011 | Installation of Laminating desktops production line of «Form&Style» at Losino-Petrovsky, Moscow Region |
Electrical design and installation supervision. Contracts management and tender works coordination. | |
2011-2012 | «FERRERO» confectionary plant , Vorsha, Vladimir region |
Leading the design and site supervision teams for installation of the Rain Water Treatment plant, internal roads construction, installation of canopies. Contracts management and tender works coordination. | |
Development of detailed design for “Recycled Waste Storage Station”. | |
2009-2013 | Historical Bldg. restoration, reconstruction & fit-out «Yakovlevy Mansion house» at Pyatnitskaya str., 58, Moscow |
Organizing concept and detailed design, investigations and construction works for the building reconstruction and restoration and for the external networks; participation to obtainment of the Expert Resolution for a Historical Building, the City Architectural Committee Booklet, several variants of architectural concepts; preparation of the Fire Safety Special Technical Conditions and getting approval from Technical Committee of MChS; contracts management, budget preparation and control. Managing construction works for external networks and substructure. | |
2008-2009 | Fit-out works at «Quantum Petroleum» company office, Vozdvizhenka str., 10, Moscow |
Project management of design and construction works. | |
2006-2008 | Reconstruction of «Russkij Karavay JSC» business-center bldg. at Sretenka str., 18, Moscow |
Leading the Investor company Construction Department. General management of all site construction and design works, including external networks; managing procurement and contractors. Control and coordination of all design documentation of the reconstructed building. Communication with foreign suppliers and contractors, the structural expertise of the skylight, organizing production and delivery of the marble decoration details, organizing manufacturing and decoration of the Atrium stucco moldings and lifts installation. |
2006 | Construction of «Car enamel plant «BASF Coаtings AG»», Pavlovsky Posad district, Moscow region |
Leading the design and the installation teams - 10 kV power supply system, electric power distribution system and electric lighting, weak current systems. | |
2006 | Construction of «Bakery & sales center «BACKALDRIN AG»», Moscow region |
Leading the design and the installation teams - electric power distribution system and electric lighting, weak current systems; HVAC and Fire Fighting systems. | |
2005-2006 | Construction of «Hotel & casino «MANSION»» building, Ostrovskogo square, 2а, St.Petersburg |
Leading the design group - electric power distribution system and electric lighting, weak current systems; HVAC and Fire Fighting systems. | |
2005-2006 | Construction of «Austrian business center» bldg., Orenburgskaya str., 4, St.Petersburg |
Leading the design and the installation teams - electric power distribution system and electric lighting, weak current systems; HVAC and Fire Fighting systems. | |
2005 | Construction of the «Skating rink of «Avanguard» hockey club, Kuibysheva str., 132/3, Omsk |
Leading the design and the installation teams - electric power distribution system and electric lighting, weak current systems; HVAC and Fire Fighting systems. | |
2005 | Fit-out works at VIP zone of the «Globex-Bank» at Novinsky Brd., 31, Moscow |
Leading the design and the installation teams - electric power distribution system and electric lighting, weak current systems. | |
2004 | «Philip Morris - Izhora» tobacco factory extension, Leningrad region |
Leading the design and the installation teams - 10 kV power supply system, 20 mW trafo substations, electric power distribution system and electric lighting of the plant. | |
2001-2003 | Construction of «Embassy of Japan» bldg., Grokholsky lane, 27, Moscow |
Site supervision for installation of electric power distribution system and electric lighting, weak current systems. | |
1999-2000 | Construction of «Moscow State University Business School» building at Leninskiye Gory, Moscow |
Site supervision for installation of electric power distribution system and electric lighting, weak current systems; HVAC and Fire Fighting systems. | |
1999 | Radiant heating systems «Fraccaro» |
Technical support to sales, certification of the series production of gas radiant heating equipment with GOST and Gosgortekhnadzor bodies for import to the Russian market. | |
1998 | Construction of «Alba Alliance» bank headquarters bldg., Kremlevskaya emb., 1, bldg.2, Moscow |
Site supervision for M&E systems installation, collection of the approvals by Energosbyt, Energonadzor and MKS, preparation of the set of building commissioning documents. | |
1997 | Reconstruction and restoration of the Apartment bldg. at Chisty lane, 10, Moscow |
M&E systems installation site supervision. | |
1996-1997 | Construction of «Gogolevsky, 11» Business-center, Moscow |
M&E systems installation site supervision. | |
1996 | Fit-out works at «CODEST Engineering» сompany Moscow office, Soymonovsky lane, 7, Moscow |
Electrical design, electrical installation supervision. | |
1995 | Construction of «Moscow Industrial Bank» bldg., Klary Tsetkin str., 20, Moscow |
Preparation of the set of commissioning documents, organizing M&E systems handing-over tests. | |
1994-1995 | Construction of «International Moscow Bank» bldg., Prechistenskaya nab., 9, Moscow |
M&E systems installation site supervision. | |
1992-1993 | Construction of «Refrigerators Plant «STINOL (Indesit)» in Lipetzk |
Assistant-Interpreter of Italian language. |
Pyotr Zuev graduated as an electronics engineer in 1992 from the “Faculty of Radio-electronics of the aircrafts” of “Moscow Aeronautic Institute” Technical University.
In 1993-1994 he took a course of studies at the “Faculty of Economics and Commerce” of the “Bergamo State University” in Italy.
2017-2018 - obtatining of the Master degree at the Moscow State University of Civil Engineering (NRU MGSU) in the area of Civil Construction
Since 2017 the engineer Pyotr Zuev has been included in the National Register of Specialists in the area of Engineering Surveys and of Architectural and Civil Design NRS NOPRIZ (# П-065510)
Since 1992 engineer Pyotr Zuev has mostly worked for a major international General Contractor and M&E companies on International construction projects in Russia as well as for Russian developers, assuming various engineering and later management positions.
In the past years he matured a wide experience in the multiple areas of construction – in the design and also the construction process either of civil or mechanical and electrical works; moreover the skills of economic and financial management of construction projects.
After being registered in 2014 as individual entrepreneur Pyotr Zuev provides expert consulting services in the field of design and construction management.